Rumia-Janowo tunnel

Construction of an integration hub in Rumia Janowo

1
2
3
4
6
5

The main task was to optimize the tunnel design solutions in order to reduce the consumption of concrete and reinforcing steel and to develop a tunnel construction technology. The tunnel was designed using the "pipe roofing" technology. The use of this method allowed for the preservation of the newly built SKM platform located above without the need to demolish it.

The whole deck, including the reinforcement, was modeled in BIM, which significantly simplified the work on its implementation.

Location: Rumia, Poland

Ordering party (Client): City of Rumia

General Contractor: Budimex S.A.

Main Designer: Lentas Sp. z o. o.

Implementation period: 2021

Total length: 30m

Date of commissioning: 2022

Galeria


20221125210004
20221025212216
10-03--HEB400-1
10-03--HEB400-2
10-03--HEB400-4
20210708183100